Switzerland has funded a Swiss pipe manufacturer to rebuild a heating network in eastern Ukraine. The pipes are the easy part.
Executive summary. On 2 October 2026 the Swiss Federal Council approved eight new reconstruction projects delivered by Swiss companies in Ukraine. The only heating project in the round went to Brugg Rohrsystem AG: CHF 19.9 million from SECO to restore a district heating network in eastern Ukraine, with training for local skilled workers built into the project. The grant is a meaningful sum for a single network. Against the condition of Ukraine’s heating sector, it is also a test case. Whether it works will depend less on the pipe and more on the people who lay it, the utility that runs it, and the contracts that hold it together.
The grant, in one paragraph
SECO’s second call for proposals offered up to CHF 150 million for Swiss companies with a legal entity in Ukraine, in grants of CHF 3 million to CHF 30 million per project. Only public infrastructure qualified: energy, water and sanitation, housing, public mobility, social infrastructure and agriculture. The Federal Council’s decision of 2 October 2026 confirmed eight projects worth CHF 135 million in energy, public transport and water. Every selected company must finance at least 10% of project costs itself.
On the published list, Brugg Rohrsystem AG is described in one line: “Restoration of the district heating network in eastern Ukraine, supplemented by training and further education for local skilled workers.” It is the only heating project in this round. We looked at all four energy projects in Part I of our Swiss–Ukrainian reconstruction series and at the round as a whole in CHF 135 Million, 8 Projects. This article goes deeper into one of them.
Why heat is a different kind of infrastructure
Electricity can be rerouted. A damaged substation can be bypassed while it is repaired. Heat cannot travel far, and it cannot wait.
District heating moves hot water through buried pipes from a central plant to apartment blocks. When the plant or a trunk line is hit in winter, the water in the system starts to cool. Below freezing, a network full of standing water becomes a network full of burst pipes. Utilities are left with one bad option: drain the system to save it, and leave the buildings cold.
That is not a hypothetical. On the night of 3 February 2026, after more than three hours of strikes on Kharkiv’s energy infrastructure, city officials drained the coolant from the heating system of 820 residential buildings supplied by one of the city’s largest combined heat and power plants. It was the only way to stop the network from freezing in severe frost.
Every repair of a district heating network in Ukraine is therefore two projects at once: restoring what was damaged, and making the system able to survive the next attack.
The network Brugg is walking into
The war did not create the problem. It sharpened one that was already there.
A 2025 sector study by the USAID-funded Energy Security Project, cited by the Danish Board of District Heating, describes the system in numbers:
- District heating operates in 116 Ukrainian communities and supplies nearly 100,000 buildings.
- Heat travels through roughly 20,900 km of pipes.
- 56% of heat networks are classified as worn out or in an emergency condition.
- 83% of large boilers have exceeded their service life.
- Around 21% of the heat produced is lost in the pipes before it reaches a customer.
Read the last figure carefully. More than a fifth of the fuel Ukraine burns for heating warms the soil, not the apartments. In wartime, when gas, coal and generating capacity are all under pressure, that loss is not just an efficiency problem. It is a security problem.
What a pipe manufacturer actually brings
Brugg Rohrsystem AG, based in Kleindöttingen in the canton of Aargau, makes pre-insulated pipe systems for district heating: flexible and rigid pipes with factory-applied insulation, designed for high temperatures and pressures.
This matters for three reasons.
1. Lower losses. Pre-insulated pipes keep heat inside the network. Replacing old, poorly insulated sections attacks the 21% loss directly.
2. Faster installation. Flexible pre-insulated pipe comes in long lengths and needs fewer joints. In a city that may need to repair the same street twice in one winter, speed of installation is a resilience feature.
3. A Swiss standard on Ukrainian ground. SECO’s model funds Swiss companies to install Swiss technology in Ukraine, with local hiring attached. The training component in this project is what turns a delivery of materials into capacity that stays.
What it will take to restore the network
The grant answers the question of money. Four other questions decide the outcome.
People
A pre-insulated network is only as good as its joints. Welding, sealing and leak-detection wiring are skilled work, and Ukraine’s utilities have been losing skilled workers to mobilisation and migration since 2022. The training clause is not a side note. It may be the most durable part of the project. If local crews can install, inspect and repair the system to the manufacturer’s standard, the network can be maintained after the Swiss team leaves.
The operator
A network is owned and run by a municipal heat utility. Its finances, tariffs and technical condition determine whether new pipe is maintained or neglected. A donor-funded section of modern pipe connected to an unreformed utility is a well-built island. The more useful question for any city receiving this kind of project is what changes in the utility’s operations, metering and repair capacity alongside it.
Design for the next winter
Rebuilding the same centralised system that a single strike can shut down is the obvious option. It is not necessarily the right one. Sector specialists now argue for networks that can be split into sections, fed from several smaller heat sources and isolated quickly when one part is damaged. Whether this project restores the old layout or builds in redundancy is a design decision that will shape how the network performs in 2027 and beyond.
Contracts and co-financing
At least 10% of the cost sits with the company. The rest of the structure is a chain of agreements: between the Swiss company and its Ukrainian entity, between that entity and the municipal utility, with local contractors and suppliers, and with the authorities that issue permits for excavation in city streets. Each link is a legal document, and each is a point where a project can slow down. Projects that define responsibilities, acceptance criteria and maintenance obligations before the first trench is dug are the ones that finish on time.
Why this matters beyond one city
Brugg’s grant is one of eight. Taken together, the second round tells Swiss and Ukrainian businesses what Bern is now willing to fund: energy, rail and water, delivered by Swiss manufacturers with a presence in Ukraine and a training component.
For Swiss companies, it confirms that heating is fundable, and that the entry ticket is a Ukrainian legal entity and a credible local delivery plan, not an expression of interest.
For Ukrainian companies, every Swiss-funded project needs local partners: installation crews, civil works, logistics, engineering supervision. Those partners are chosen before the money arrives.
For municipalities and utilities, the lesson is that donor projects reward readiness. A city with a clear technical plan, a cooperative utility and a defined maintenance model is a better partner than one with the greatest need and no plan.
The Lighthouse perspective
District heating is where reconstruction becomes personal. A substation is abstract to most people. A cold radiator in February is not.
CHF 19.9 million will not fix Ukraine’s heating sector. It can show what a well-structured project looks like: Swiss technology, local skills, a utility that can run what is built, and contracts that make every party’s obligations clear. If that model works in one eastern Ukrainian network, it becomes a template for the next call and for the cities still waiting.
The pipe will arrive. The question is whether everything around it is ready.
Working on an energy or infrastructure project between Switzerland and Ukraine? We advise on structuring Swiss–Ukrainian partnerships, local entities and project contracts. Write to us at info@lighthouse-legal.eu.